Bad Weather Extends Blind Pass Dredging Project
Posted by Sandy Ramseth on Jul 10, 2009 in Blind Pass Dredging | 0 commentsWell, here’s the latest and greatest on our Blind Pass Dredging Project as of the July 3rd update:
- The last half of June unfortunately did not cooperate weather-wise in letting Dredge Nate out into the Gulf to finish its work, and therefore, has prompted a request to Lee County for a two-week extension to get the job finished up properly.
- The “Pole and Troll” buoys haven’t been placed as of yet, but when they are placed in Wulfert Flats, enforcement of the zone will go immediately into effect.
- Expected date of project completion is now anticipated for July 25th barring that the weather cooperates.
You can read all the details below or simply download the entire pdf document right here: July 3rd Blind Pass Update